Item |
Total Price |
| |
Building a Barn |
|
| 1 |
Developing technical specifications and surveying |
3000 |
| 2 |
Cutting and transporting wood |
12000 |
| 3 |
Buying and transporting other building materials |
30000 |
| 4 |
Building the barn |
15000 |
| |
Sub-Total Russian Roubles to build a barn |
60000 |
| |
|
|
| |
Building a Coral |
|
| 1 |
Building materials |
6000 |
| 2 |
Construction work |
9000 |
| |
Sub-Total Russian Roubles to build a coral |
15000 |
| |
|
|
| |
Buying Livestock |
|
| 1 |
5 Sheep |
7500 |
| 2 |
2 Horses |
30000 |
| 3 |
Sled |
4500 |
| 4 |
Wagon |
3000 |
| |
Sub-Total Russian Roubles to buy livestock |
45000 |
| |
|
|
| |
Total Russian Roubles |
120000 |
| |
Total US Dollars (exchange $1 = 30 RR) |
$4,000 |
* This is a preliminary budget. The numbers will be finalized after completing the first step.